Change Orders on a Commercial Paint Job

2 min read

A commercial painting change order is a written change to the scope, priced before the crew does the work. Added frames, a stairwell nobody walked, a color the board picks after the benchmark, and peel that was behind a cabinet all qualify. A verbal “while you’re here” does not. The clause that requires the writing sits in what belongs in a commercial painting contract. The number it changes is the one screened in commercial painting cost per square foot.

Price it from lines you already published

The clean change order uses a unit price from the bid: per door and frame, per color, per square foot of unforeseen peel or patch, per extra mobilization. What a commercial painting estimate should itemize is where those units belong, before anyone finds the extra work.

Where the bid has no unit, the change order states labor and material at a rate the contract already named, or a lump sum for a described area. A rate invented on the day of the work is an argument. A rate in the contract is arithmetic.

Separate a change from a miss

Three things get called change orders and only one of them is:

  • Added scope. A surface, a color, a floor, or an hour that was excluded or never walked. That is a change order.
  • A condition the scope already included. Peel on an elevation the bid said it would scrape and prime is not extra. It is the job.
  • A condition both sides excluded. Lead, a wet wall, a roof leak, or a substrate the proposal said would be tested or repaired by others. That stays excluded until there is a new written scope. It is not “included now, we’ll sort the price later.”

If two bids treated the same peel differently, fix the comparison before you award. Questions that make two commercial painting bids comparable is that check. Awarding the low number and then buying the missing prep as a change order is how the low number wins twice.

Who may sign, and when

Name the person who can approve a change, and the dollar amount they can approve without going back to the owner or the board. A superintendent and a night foreman should not discover, after the wing is coated, that neither of them could spend the money.

Time is part of the price. An added stairwell on an occupied floor can add a mobilization and push the date a tenant returns. The change order should say whether the finish date moves. A price with a silent schedule is how a three-night add becomes a two-week slip.

Do the work after the paper, not before. Painting first and pricing second leaves the owner with a finished wall and the contractor with an unpaid invoice, and neither document matches the contract.