School and Campus Painting
School painting is occupied-building work on a calendar the district does not control. Summer, winter break, nights, and weekends are the hours a crew can have a corridor. A bid that assumes an empty semester will not survive the first week of class. Hire against that calendar the same way you would any other commercial scope, in how to hire a commercial painting contractor.
The calendar is the scope
Write which buildings, which rooms, and which dates. A gym that can close for three weeks in June and a classroom wing that can only be coated on nights in October are different crew plans. Count mobilizations. A campus of eight buildings is eight starts unless the proposal says a crew stays and moves.
Hallways, classrooms, cafeterias, locker rooms, and the exterior are different systems. Flat on a classroom ceiling, a washable sheen on a corridor, and a masonry coating on a gym wall do not share a spread rate. Ask for them as lines. Interior commercial painting cost is the method for the rooms. Exterior commercial painting cost is the method for the shell.
Occupied days still happen
Summer projects still share the building with camps, maintenance, and teachers setting up. Notice, protection of floors and furniture, and a morning the room has to be usable are the same rules as painting an occupied building. Restrooms and kitchens add the health rules for those rooms. Do not leave them inside a “paint the school” sentence.
Security and badging are access, not a courtesy. Say who sponsors the crew, which gates they use, and whether a district employee has to be on site after hours. A price that assumes open doors will burn the first night on a locked corridor.
Older paint is a test, not a sanding job
Schools built before 1978, and many later than that, can still carry lead-containing coatings on doors, frames, trim, and exterior wood. Sanding, grinding, or heat-softening those coatings is a regulated disturbance, not prep. If the district does not have a report, exclude disturbance of existing coatings until there is a test, and price an encapsulating recoat only where the spec allows it. The same exclusion belongs in any commercial bid on an old building. How to read a commercial paint specification flags it when the project manual is silent.
Public schools often buy this work on a solicitation: a bid form, addenda, insurance, and sometimes a bond and a wage determination. Painters pricing that packet should read insurance, bonding, and prevailing wage on public work before they fill in the blank. Owners comparing the replies still want one scope. The low form that skipped the nights or the lead exclusion is a different job.
Describe the campus and choose Commercial when you want one contractor to price the calendar you can offer.